Tech Perspective / Semiconductor Factory Construction

What It Costs to Build a Semiconductor Fab

What exactly did the hundreds of billions of dollars mentioned in factory construction news buy? This article breaks down publicly available investment cases into factory buildings, equipment, shared facilities, and pilot production, avoiding mistaking the total cost of the industrial park for the cost of a single factory.

Published:

Original concept illustrations of a wafer fab building and the morning light source referenced by Hope

ARTIST REFERENCE / Artist Introduction

Edward Hope

Edward Hopper

American realist painting, architectural geometry, and the interplay of light and shadow.

John Hope (1882–1967) was an American painter and printmaker who lived and worked in New York for many years. He drew inspiration from streets, offices, homes, and coastal landscapes, using clear geometric compositions and light and shadow to present the silence and psychological tension in everyday scenes.

Style reference ・ Original concept art, not the artist's own work or a specific factory site scene.Biography

First, align the investment scope.

Even when it comes to factory construction investment, some figures only refer to one factory, while others include several factories, shared facilities, and subsequent expansions. Read the scope of the announcement first, then compare hundreds of billions of dollars.

The tasks of wafer fabrication and packaging/testing are also different: one forms components and interconnects, while the other connects integration and testing. Equipment, capacity specifications, and facility configurations are not directly interchangeable.

Investment amounts only become meaningful for comparison after the product, manufacturing process, planned capacity, and construction scope are determined.

Four publicly disclosed cases: first look at the scale, then the numbers.

The table below retains the announced plans for each company in a specified year for comparing investment scope. These are planned or projected expenditures at that time, not final settlements, and do not include all subsequent expansion announcements.

Case and Announcement YearAnnouncement of investment amountCalculation Scope
TI Lehi/2023US$11 billionAdding a new 300 mm wafer fab; integrating with existing fabs[1]
JASM Kumamoto / 2024Over US$20 billionCombined first and second wafer fabs[2]
TSMC Arizona / 2024Over US$65 billionAt that time, the base capital expenditure of the three wafer fab plan[3]
Amkor Arizona / 2025US$7 billionTwo-phase advanced packaging and testing campus[4]

For example, JASM's figures are for both plants combined; TSMC Arizona's figures are for a three-plant plan by 2024, with further expansion announcements to follow. Amkor's $7 billion figure covers the two-phase campus, not the construction costs of a single packaging plant.

Shared facilities, different factory sizes, and equipment configurations all affect the costs of each factory. Dividing the total cost by the number of factories only yields an arithmetic average and cannot be considered a single factory price.

The machine and the entire building supporting it

In Intel's publicly available layout, in addition to the manufacturing floor, there are air handling units, sub-fabs, and utilities. The machines that engineers see in the cleanroom rely on these spaces for continuous supply and support.

Vacuum pumps, chemical valve boxes, and electromechanical and power distribution systems all require locations and connections. Sensitive equipment also requires vibration control, thus the floor slabs and structures differ from those of general buildings.

[6]
Figure 1 | Conceptual cross-section of a wafer fab, compiled based on Intel's publicly available layout.
Figure 1 | Conceptual cross-section of a wafer fab, compiled based on Intel's publicly available layout. Dot plots reveal the full dimensions.

Machines within cleanrooms also require power, ultrapure water, gas, and chemical supplies; wafers move between equipment via automated handling systems. These connections must be integrated with the equipment and production processes and cannot be simply understood as the water and electricity configurations of a general building.

[7]

Equipment and plant facilities are central to cost understanding.

Intel's 2022 plant construction diagram describes a factory with approximately 1,200 process equipment and 1,500 utility installations. This is a company-specific scale example, not a fixed configuration for every wafer fab, but it clearly illustrates the complexity of the setup work.

[5]

After purchasing exposure, deposition, etching, cleaning, grinding, and measurement equipment, it's necessary to move it in, connect it to the system, install it, and calibrate it. Once a single machine passes testing, the next step is to verify its compatibility with the entire process.

Figure 2 | Key observation items in the factory construction budget; the area of ​​the square does not represent the cost ratio.
Figure 2 | Key observations for plant construction budget; the area of ​​the squares does not represent the cost percentage. Dot plots can be used to view the full size.

The figures list budget observations without accounting classification. How pilot production, validation, or R&D expenditures are recognized still needs to be determined according to their actual nature and applicable standards.

Why are there such big differences between different locations and different plans?

First is scale and technology mix. JASM's 2024 announcement listed the combined capacity and various processes of the two fabs; TSMC's Arizona announcement in the same year described the cleanroom area and technology plan of its advanced fab. Even though they're all called "wafer fabs," their actual contents differ.

[2] [3]

Whether existing facilities can be shared within the same site also affects investment. When the factory is completed first and equipment is moved in in stages, the expenditures in each year will not be equal to the total project cost.

There are also differences in land, construction, supply chain, exchange rates, and subsidy standards across regions. Without comparable details, the price difference cannot be attributed entirely to one reason.

Costs from completion to operation

After the factory is built, equipment may still be being moved in. After integration, process conditions are established, products and quality are verified, and production stability is gradually improved. There is inherently a time lag between completion and production.

Figure 3 | Different milestones from construction to mass production; actual work may be carried out in stages and overlaps.
Figure 3 | Different milestones from construction to mass production; actual work may be carried out in stages and overlapping. Click the graph to open the full dimensions.

Amkor's 2025 announcement lists the expected completion and production times for the first manufacturing facility. This writing style reminds us that the completion date of a project and the start date of production are not necessarily the same.

[4]

After production begins, there are still costs for materials, energy, personnel, maintenance, and depreciation. Yield determines the deliverable quantity, and utilization affects the allocation of fixed costs; therefore, knowing only the construction cost does not allow us to calculate how long it will take to break even.

Total investment, subsidies, and operating costs should be read separately.

Total investment is the project scale, subsidies and tax breaks are support methods, and investment and loans are sources of funds. They cannot be added together, nor can they be considered as the same cost.

In its 2024 Arizona Announcement, TSMC separately explained base capital expenditures, the then-proposed direct subsidies, loans, and investment tax credits. This is an example of identifying different definitions; the then-proposed conditions should not be taken as the final amount received.

[3]

Annual capital expenditures also have their own scope. The company's annual report will explain the overall investment and financial results, but the company's annual expenditures may be distributed across multiple plants, equipment, and other projects, and cannot all be attributed to a single new plant.

[8]

Record the announcement year, project stage, equipment scope, and planned or actual expenditure amount next to the amount. If any of these items are missing, leave the comparison open and don't rush to conclude which region is cheaper.

Sources and Further Reading

  1. Texas Instruments: Investment Announcement for New 300mm Wafer Fab in Lehi (February 15, 2023) ↗
  2. TSMC: JASM Kumamoto Fab 2 and Total Investment of Both Fabs (February 6, 2024) ↗
  3. TSMC: Arizona Fab 3 Plan and Base Capital Expenditure (April 8, 2024) ↗
  4. Amkor: Arizona Two-Phase Advanced Packaging and Testing Campus (October 6, 2025) ↗
  5. Intel: What does it take to build a fab? (Illustrated Guide to 2022) ↗
  6. Intel: Fab Floor and Facility Layout ↗
  7. Intel: Cleanrooms, Process Equipment, and Automated Handling ↗
  8. TSMC: 2025 Annual Report ↗
  9. Whitney Museum: The Life and Works of Edward Hopper ↗